Potmans Lane BESS

49.9MW G99 Type D connection with power factor correction sizing

Project Overview

Potmans Lane is a 49.9MW battery energy storage system in East Sussex, connecting to the UKPN 132kV network. Like Halesworth, it's classified as Type D due to the high connection voltage.

What made this project unique was the discovery during studies that the battery inverters alone couldn't achieve the required power factor at full 49.9MW export. This required us to design a power factor correction solution to reach full capacity while maintaining G99 compliance.

The Challenge

During the load flow and reactive power analysis, we identified that the selected battery inverters had insufficient reactive power capability at full active power output. Without intervention, the project would either fail G99 compliance or be forced to curtail active power export.

The challenge was compounded by equipment changes during the project—the PCS (Power Conversion System) changed mid-project, requiring multiple design iterations.

Additionally, the project required NER (Neutral Earthing Resistor) sizing for transformer earth fault protection, adding another layer of complexity to the design.

Our Approach

We delivered the full G99 Type D package plus a dedicated PFC sizing study to resolve the reactive power limitation.

G99 Studies

  • G99 Load Flow Study
  • Short Circuit Study
  • P28 Voltage Fluctuation Study
  • G5/4 Harmonic Study
  • Cable Sizing Study
  • NER Sizing Study
  • Dynamic Study (RMS simulation)

Protection Studies

  • OCEF (Overcurrent Earth Fault)
  • SBEF (Standby Earth Fault)
  • Transformer Bias Differential
  • Transformer HV REF
  • Transformer LV REF

PFC Sizing Study

Dedicated power factor correction analysis to determine the required capacitor bank sizing:

  • Reactive power gap analysis at full export
  • Capacitor bank sizing calculations
  • Harmonic impact assessment
  • Integration with overall plant design

Technical Highlights

PFC Sizing

Identified inverter reactive power limitation and designed capacitor bank solution to achieve full 49.9MW export with G99 compliance.

NER Sizing

Neutral earthing resistor sizing for transformer earth fault protection, ensuring safe fault current limitation.

Design Iterations

Multiple design rounds as equipment changed mid-project, maintaining compliance through PCS changes.

132kV Expertise

High voltage connection with full transformer protection suite and UKPN coordination.

Problem Solving in Action

This project demonstrates our approach to technical problem-solving. Rather than simply reporting that the inverters couldn't meet requirements, we identified the specific shortfall, designed a practical solution (PFC capacitor bank), and delivered a compliant design that achieved the project's full capacity target.

Results

The project achieved UKPN approval with the PFC solution in place, enabling full 49.9MW export capacity. The BESS is now fully operational.

"Completed for Smith Brothers"

Key Facts

Capacity
49.9 MW
Connection Voltage
132 kV
G99 Classification
Type D
Location
East Sussex, England
DNO
UKPN
Completion
2023
Status
Operational

Facing similar challenges?

We identify and solve technical problems to achieve your project's full potential.

Get Your Quote

Need Professional Support?

Our Chartered Engineers deliver complete G99 compliance packages, protection coordination studies, and power system analysis for UK renewable energy projects.